Virtual PPA vs On-site PPA: When Each Wins
Virtual (synthetic) PPAs and on-site PPAs solve different problems. Decision framework with example p&l for each.
Deciding whether a PPA fits your site? Run the two-minute suitability check or send your site details.
Two products with the same name, different problems
On-site PPA: generator builds solar on your roof. Virtual PPA: financial contract referencing a wholesale price. Both called "PPA" — totally different mechanics.
When on-site wins
- Single site with 200kWp+ of useable roof
- Long site tenure (15+ years)
- Simple business — single-site SME, regional manufacturer
- Want directly-attributable kWh savings
- Strong daytime load profile
When virtual wins
- Investment-grade corporate, >£10m annual electricity spend
- Multi-site or geographic mismatch with solar resource
- Treasury sophistication (IFRS 9 hedge accounting capability)
- Want pure financial hedge against wholesale prices
- Need REGO certificates separate from any specific site
Side-by-side
| On-site PPA | Virtual PPA | |
|---|---|---|
| Physical kWh delivery | Yes | No |
| Site survey | Required | Not relevant |
| Year-1 tariff | 9-18 p/kWh | £55-75/MWh strike |
| System size | 50kWp-5MWp | 10MWp+ typical |
| Counterparty | Local SPV | Wholesale generator |
| Term | 15-25 years | 10-15 years |
| Accounting | Operating expense | Hedge accounting (IFRS 9) |
| Roof rights needed | Yes | No |
See what tariff your site qualifies for
A 60-second form gives us enough to review your site. We reply by email.
Get an indicative PPA tariffIf the financial route is the one you are weighing, our full guide to the virtual PPA covers settlement, basis risk and the accounting changes that apply from 2026.