UK Solar PPA RFP Template
A procurement-grade RFP structure for UK commercial off-takers going to market for a solar PPA. Six sections covering site overview, commercial terms, technical scope, off-taker info, bidder questions and evaluation matrix.
Section 1: Site overview
- Site address + postcode
- Site lease/freehold status and remaining term
- Year of construction
- Roof area (m²) and orientation
- Roof age and condition assessment available?
- Annual electricity consumption (last 12 months kWh)
- Half-hourly profile if available
- Current import tariff (p/kWh)
- DNO connection capacity if known
- Planning history
- Listed status / heritage considerations
Section 2: Commercial terms required
- Required term length (15/20/25 year preference)
- Escalator preference (fixed / RPI / CPI / zero)
- Contract structure preference (on-site / sleeved / corporate)
- System size range expected
- REGO transfer required: yes / no
- Battery storage required: yes / no
- SEG income allocation: off-taker / provider
Section 3: Technical scope
- Performance ratio guarantee (78%+ required)
- O&M scope minimum (monitoring, cleaning, replacement, insurance)
- M&V protocol (IPMVP Option B preferred)
- Monitoring access for off-taker
- Panel and inverter brand acceptance list
Section 4: Off-taker information
- Company structure (UK Ltd / PLC / charity / public sector)
- Audited accounts last 3 years (provided in data room)
- Parent guarantee availability
- Business horizon at this site
- Sector + sub-sector
- ESG / sustainability commitments
Section 5: Bidder questions
- Provider experience with comparable sites (3 references)
- Funding structure for the SPV
- EPC contractor proposed
- O&M provider proposed
- Indicative tariff range (year 1)
- Escalator type proposed
- Term length proposed
- End-of-term options proposed
- Lead time from heads-of-terms to commissioning
Section 6: Evaluation matrix
Suggested weighting:
| Criterion | Weight |
| Year-1 tariff (lower = better) | 30% |
| 25-year cumulative cost (LCOE) | 15% |
| Term flexibility | 10% |
| Technical scope | 15% |
| References (3 deals) | 15% |
| Provider quality (financial standing, ESG, governance) | 10% |
| End-of-term option attractiveness | 5% |
Process timeline
- Week 0: RFP issued to 3-4 pre-vetted providers
- Week 2: Bidder questions deadline
- Week 3: Provider site visits
- Week 6: Indicative bids in
- Week 8: Shortlist of 2 invited to BAFO
- Week 12: Preferred bidder selected
- Month 4-6: Heads-of-terms negotiation
- Month 7-9: Full contract execution
- Month 10-12: Build